除夕的一場雨,恰逢工地欠缺人手工具,幾乎弄得值班人員人仰馬翻,
其實,Building Weather Tight 應該是整個工程(PROJECT)的一個重要里程碑,
根據電氣工程師指出: 在高壓電纜尚未接入設備並密封之前,電纜頭不能碰到水!
另外,已經進場的一些控制電箱,更有濕度要求,如果房間進水了,濕度會失控.
在1/4 的 一場討論預定進度的會議上,
people said that we have a lack of schedule controlling to the contractor due to no milestones be mentioned in the contract.
however, the reason for no milestones in the contract might because they had no plan at that moment.
therefore, a proper strategy and the following planning are very important and critical for project success.
發現到"成品保護"這件事是需要被刻意放進工作範圍, 並且需要考慮涉及到幾種不同情境下所需要的"保護等級"